Document - Enloe Decision PCHB NO. 12-082

Abstract

The §401 Certification is affirmed, subject to the additional condition that 10/30 cfs minimum instream flows over the Dam and Falls for the aesthetic values shall be further monitored and evaluated by Ecology during initial operation of the Project (within three years). After Ecology obtains additional data and analysis of alternative flows over the Dam and the Falls, the 10/30 cfs flow shall either be confirmed or revised as a condition of project operation and the §401 Certification.

Description

Decision on aesthetic flows for the proposed Enloe Hydroelectric Project.