Management Plan submitted for Upper Colorado River (CO)
Colorado - The Upper Colorado River Wild and Scenic Stakeholder Group represents a diverse range of interests who have worked together since 2007 to develop an Upper Colorado River Wild and Scenic Management Plan to protect the outstandingly remarkable values (ORVs) identified in the U.S. Bureau of Land Management (BLM) and U.S. Forest Service (USFS) Eligibility Reports for Segments 4 through 7 of the Upper Colorado River.
The SG Plan is being proposed to BLM and the USFS as a potential Wild and Scenic Rivers
management alternative for the resource management plan revision process. The Stakeholder
Group’s intention for this collaborative Plan is to balance permanent protection of the
ORVs, certainty for the stakeholders, water project yield, and flexibility for water users. A
significant benefit of the SG Plan is that through the cooperative and voluntary efforts of
interested water users, local governments, and other entities, the ORVs can be protected (and
perhaps enhanced) in ways that coordinate with federal agency management.
The SG Plan will use identified Long-Term Protection Measures and voluntary Cooperative Measures
of the Stakeholder Group to protect the ORVs. Examples of the protective measures include the
appropriation of a Colorado Water Conservation Board (CWCB) Instream Flow (ISF) water right,
delivery of water to senior water demands downstream of Segments 4 through 7, and water
deliveries to the 15-Mile Reach in the Grand Valley pursuant to the Upper Colorado River
Endangered Fish Recovery Program.
The SG Plan aims to protect all ORVs while focusing on recreational fishing (in Segments 4
through 6) and recreational floatboating (in Segments 4 through 7). The SG Plan uses two distinct
tools – “ORV Indicators” (characterizing the range and quality of the ORVs)
which will be used to gage whether the ORVs are being protected; and “Resource
Guides” (reflecting ranges for factors such as flow, temperature and water quality) that
will be used as a source of information among others to inform SG discussions under the Plan.
The SG Plan’s implementation procedures will provide a feedback loop to periodically
confirm that the management measures under the SG Plan, in coordination with BLM’s and
USFS’s other land management actions, are protective of all ORVs. The SG Plan contains
mechanisms to address concerns related to impairment of or a significant risk of impairment to
the ORVs.
The effective date of the SG Plan will commence upon issuance of records of decision by BLM and
the USFS approving the Plan without material change as the Wild and Scenic Rivers management
alternative for Segments 4 through 7 of the Upper Colorado River. A formal endorsement of the
Plan by the Stakeholder Group shall be provided no later than April 30, 2011.
Full Text of the Upper Colorado River Management Plan can be found here.
Nathan Fey
1601 Longs Peak Ave.
Longmont, CO 80501